Short answer
Usually not if you want the costs covered. Most programs only reimburse costs incurred after the approval letter or agreement and within the project dates. IAF's 2026/27 guide is explicit: costs incurred before you receive a project approval letter won't be reimbursed, and nothing retroactive is considered.
What you can safely do before approval
- Collect quotes and scope the project
- Gather records, licences and documents for the application
- Plan the timeline so the work fits within the project deadline after approval
What to avoid before approval
- Signing a non-cancellable contract or paying a deposit you plan to claim
- Starting the consultant's assessment or training
- Ordering equipment you want funded
Common mistakes
- Thinking an "eligible" email or an application receipt is approval.
- Approval arriving close to the completion deadline, leaving too little time for the work.